2022 Pavement Maintenance Project
Resolution No. R21-74
Task Order between City of Laurel and KLJ Engineering Inc. to authorize service for the 2022 Pavement Maintenance Project.
Passed/Approved 08-24-2021
Project Type: Project Status: Location:
Reconstruction S. 4th Street section, Approved/Preliminary Stage South Side
Water, and Sewer Date Received: Laurel, MT 59044
Tuesday, August 24, 2021 See Map:
Description:
Project consists of removal and replacement of the existing waterline within S. 4th Street, removal and replacement of the crossing sewer pipes, and reconstruction of the street section on S. 4th Street from US Highway 212 to S. 8th Ave.
The water and sewer mains within the street have also been identified as being at the end of their service life. The approximate Right-of-Way width in the area is 60-ft and existing street width is 34-ft as measured from the back of curb.
This project will include approximately 2,600 lf of 8” water main, 400 lf of 8” sewer main, 8 fire hydrants, 5 sanitary sewer manholes, and 2, 600 lf of street reconstruction.
Timeline:
Desire construction to occur between May 1, 2022 and September 30, 2022.
Budget:
Task Order total for services rendered is $595,800.00. This is divided between Streets Maintenance, Water, and Sewer.
Layout:
None