East Downtown Infrastructure Improvements

Project ID: 
Completed
Project Type:
Infrastructure
Project Status: 
Approved
Date Received: 
Monday, April 13, 2020
Location: 
East Downtown Infrastructure Improvement Project Laurel, MT 59044

Description:

Reconstruction of Washington, Idaho and Ohio Avenues, E. First and E. Fourth Streets; generally bound by Wyoming and Alder Avenues, Main and E. Fourth Streets with a new urban street section, including curb and gutter, sidewalk, pedestrian ramps, driveway approaches and new asphalt pavement; replacement of existing water mains, including valves, fittings, fire hydrants and other appurtenances; replacement of existing sanitary sewer main; and installation of a new storm drain system, including inlets, manholes and appurtenances.

Timeline: 

The East Downtown Infrastructure Improvement Project started on April 13, 2020, and is expected to be completed by September 2020. There will be various road closures associated with this project. 

Budget:

Contract was awarded to Knife River Construction for an overall budget of $2,487,572.50.  Bid was broken down as follows:  Schedule 2 Street Improvements $1,378,523.70; Schedule 3 Storm Drain Improvements $349,272.80; Schedule 4 Water Improvements $580,172.00; Schedule 5 Sanitary Sewer $179,604.00.

The EDII project is funded through the Tax Increment Finance District (TIF District) by a bond sold to Western Security Bank. Bonding for this project will extend the life of the TIF District an additional 25-years allowing the Laurel Urban Renewal Agency to continue to support growth and improvements within the District.

Layout: 

Attached as the EDII General Layout.

Alder Avenue Flooding Every Time It Rains
Alligator Cracked Pavement 01
Alligator Cracking In Pavement 02
Collapsed Culverts 01
Collapsed Culverts 02
Cracked and Uneven Sidewalks 01
Cracked and Uneven Sidewalks 02
Cracked and Uneven Sidewalks 03
Curb and Gutter in Disrepair 01
Curb and Gutter in Disrepair 02
Curb and Gutter in Disrepair 03
Curb and Gutter in Disrepair 04
No ADA Ramp 01
No ADA Ramp 02
No ADA Ramp 03
No Sidewalk Connectivity or ADA Ramps on Alder, East 1st Street, and Ohio
Street Pavement by High Plains Brewery
Poor Drainage/Flooding Issues 01
Poor Drainage/Flooding Issues 02
Poor Drainage/Flooding Issues 03
Poor Drainage/Flooding Issues 04
Poor Drainage/Flooding Issues 05
Poor Drainage/Flooding Issues 06
Poor Drainage/Flooding Issues 07
Poor Drainage/Flooding Issues 08
Poor Drainage/Flooding Issues 09
Poor Drainage/Flooding Issues 10
Poor Drainage/Flooding Issues 11
Poor Drainage/Flooding Issues 12
Poor Drainage/Flooding Issues 13
Vegetation Blight 01
Vegetation Blight 02
Curb and Gutter in Disrepair 05
Curb and Gutter in Disrepair 06
Curb and Gutter in Disrepair 07
Cracked and Uneven Sidewalks 04
Cracked and Uneven Sidewalks 05
Cracked and Uneven Sidewalks 06
Curb and Gutter in Disrepair 08
Street in Disrepair 01
Cracked and Uneven Sidewalks 07
Curb and Gutter in Disrepair 09
Curb and Gutter in Disrepair 09
Vegetation Blight 03
Vegetation Blight 04
Vegetation Blight 05
Curb and Gutter in Disrepair 10
Curb and Gutter in Disrepair 11
Curb and Gutter in Disrepair 12
Vegetation Blight 06
Vegetation Blight 07
Curb and Gutter in Disrepair 12
Curb and Gutter in Disrepair 13
Curb and Gutter in Disrepair 14
Curb and Gutter in Disrepair 15
Street in Disrepair 02
Poor Drainage/Flooding Issues 14
Curb and Gutter in Disrepair 16
Curb and Gutter in Disrepair 17
Poor Drainage/Flooding Issues 15
Poor Drainage/Flooding Issues 16
Poor Drainage/Flooding Issues 17
Poor Drainage/Flooding Issues 18
Start of Construction EDII Project 02
Start of Construction EDII Project 01
Start of Construction EDII Project 03
Installing Water Main 01
Installing Water Main 02
Installing Water Main 03
Installing Water Main 04
Installing Water Main 05
Installing Water Main 06
Installing Water Main 07
Installing Water Main 08
Installing Water Main 09
Installing Water Main 10
Bolt Corrosion on Water Main Replacement 01
Work on East Main Street to connect a new waterline in Idaho Ave.
EDII
Abandoned Water Main
Bolt #2
EDII Project
EDII Project
EDII Project
EDII Project
EDII Project
New Infrastructure
Old Infrastructure
Old Infrastructure
Old Infrastructure
Old Infrastructure
Old Infrastructure
Old Infrastructure
Old Infrastructure
New Infrastructure
Old Infrastructure
Old Infrastructure
Old Infrastructure
Old Infrastructure
Old Infrastructure
EDII Project
EDII Project
EDII Project
EDII Project
EDII Project
Status Updates

Week of April 27:

Installing new water valves and replacing undersized water mains in East Downtown.  The project will provide better water flows for fire suppression and looped water lines for better water quality.

Week of May 4:

Water line installation on East Main Street and Idaho Avenue.  The City is installing new water main from East Main Street to East 1St Street on Idaho Avenue.  This city block only had an undersized  four inch water main that spanned only for half the block.  The water line was not looped and homes were on the dead end water line.  All water lines, when possible, should be looped in order to maintain water quality and to provide for sufficient water volume and pressures for fire suppression.  During installation the contractor removed an old wood water main that had been abandoned years ago.  The new water line will increase flows to this area and allow for water movement thus increasing the water quality.

Week of May 11:

Work continues on storm drain installation on Washington and Idaho Avenues.  Sanitary sewer installation is being completed on Idaho Avenue this week. Concrete curb, gutter and sidewalk removal has started.

Updated Status: September 9, 2021

This project has been completed.

 

Files: