Water Treatment Plant Lift Well Replacement Project
Resolution No. R21-05
Resolution of City Council approving a Task Order between the City of Laurel and KLJ Engineering Inc to authorize work for the Water Treatment Plant Lift Well Replacement Project.
Passed/Approved 01-26-2021
Project Type: Project Status: Location:
Water Treatment Plant Approved/Current Water Treatment Plant
Lift Well Replacement Project Date Received: Laurel, MT 59044
Tuesday, January 26, 2021 See Map: none
Description:
Project consists of the replacement of the Lift Well at the Laurel Water Treatment Plant (replace well sump pump). It is a concrete culvert that goes down into the ground that has a pump installed. Unlike a sewer lift station, it lifts the water to our pond from the water plant. During the treatment process, they lift water off the bottom of the new SED basins, off the floor drains and rain gutters of the building. Then it goes into this wet well and then is pumped up to the pond. Believed the pump was installed in 1978.
Objective is to get two pumps installed, for redundancy.
When rebuilding, need to ensure the wet well is built below the floor drains of the SED basins to dispose of the mud and sediment.
Timeline:
Project planned for mid to late summer and is expected to cost approximately, $690,000.00.
Budget:
Task Order for services rendered for this project is $139,654.00.